BREAKING: Ishraque Hossain made DSCC mayor      No holidays for police during Eid: Home secy      Prof Yunus meets China Executive Vice Premier      Asian countries must chart roadmap for shared future: Yunus       GK Shamim jailed for 5.5yrs in 2.97 billion graft case      Trump extends felicitation to Yunus, pledges to strengthen mutual relations      Last day of bank transaction      

Barapukuria Power Plant halts operations amid mechanical failures

Published : Wednesday, 19 February, 2025 at 11:36 PM  Count : 560

The Barapukuria Power Plant in Dinajpur has been forced to cease operations entirely due to multiple mechanical failures, including a boiler leakage, officials confirmed on Wednesday.

Abu Bakkar Siddique, the plant's chief engineer, stated, "Since the issue is mechanical, it is difficult to predict when operations will resume. We are currently procuring the necessary equipment for repairs domestically."
The 525MW plant has seen all three of its units shut down due to separate technical issues. Unit 1 (125MW) experienced a boiler pipe leakage on Tuesday, while Unit 3 (275MW) encountered a pipe and bearing failure on February 15. Unit 2 (125MW) has been non-operational for several months due to a prior mechanical fault.

The shutdown has raised concerns about power supply in the region, with authorities working to expedite repairs and restore operations as soon as possible.


LATEST NEWS
MOST READ
Also read
Editor : Iqbal Sobhan Chowdhury
Published by the Editor on behalf of the Observer Ltd. from Globe Printers, 24/A, New Eskaton Road, Ramna, Dhaka.
Editorial, News and Commercial Offices : Aziz Bhaban (2nd floor), 93, Motijheel C/A, Dhaka-1000.
Phone: PABX- 41053001-06; Online: 41053014; Advertisement: 41053012.
E-mail: [email protected], news©dailyobserverbd.com, advertisement©dailyobserverbd.com, For Online Edition: mailobserverbd©gmail.com
🔝
close